The green peas frying machine needs to be installed before its normal use. How is the installation process of the machine?Today I'd like to introduce you to the installation of the green peas frying machine.
Green Peas Frying Machine For Sale

1. Firstly, we need to connect the automatic temperature control meter box, blower, hoist motor, clean slag pump, total power supply, check the frying basket to rise, the decrease of the green peas frying machine should be normal.
2. Then we will close the connection pipe of the dregs oil pump and the fryer, and start to irrigate the pan with the iron slag, rust, garbage and other sundries in the frying pan, and release it through the mouth.
3. Then we should set up the oil pump and Fried pipeline connection pipe, check the slag removal pump and deep fryer all pipes and joints don't leak, the slag removal filter package in slag removal filter barrels, oil and then put into the container.Use a dregs oil pump to pump oil into the green peas frying machine (oil is 15 centimeters high) and soak the electric parts of the meter box in the cooking oil.
4. Then we can start the ignition, lit with dry wood coaling after (with more than 7000 calories of anthracite), blower (350w-550w), start small air combustion, the oil temperature reaches 165-180 ℃, blower all airflow into the wind.
5. In the end we can check the meter box of electrothermal accidentally metal parts is soaked in oil, the temperature control display is normal, the temperature indicates the temperature dial to the number in the you need the pot (130-190 ℃).
This is the assembly of the green peas fryer machine. If you have any other questions, contact me in time for the green peas fryer machine.

Website: http://www.fried-machinery.com/products/frying-line/green-peas-production-line.html
Email:ellie@machinehall.com]
Skype:leo.liufan
Whatsapp:+8618595717505

Comments

Hot Blogger

How to Operate Groundnut Frying Machine Safely?

Groundnut Frying Machine Brief Introduction